In data center site selection, the power supply comes first.

Data center site selection turns on a few things that rarely sit together: a utility that can deliver a city sized load on a known date, land near high voltage lines, water or a cooling design the county accepts, and diverse fiber routes. We find and check sites, compare and negotiate the power and water supply, and negotiate the incentives.

A data hall in section: a row of racks on a raised floor, a cooling unit, a cable tray and the busway overhead
  • Large new campuses draw 100 to 1,000 megawatts
  • As much load as 80,000 to 800,000 homes
  • Servers are replaced every few years
01 What the plant needs

A data center campus needs power before anything else.

Three kinds of company build campuses: cloud providers for their own services, AI companies for training models, and colocation developers who lease space and power to tenants. The table describes a large campus of any of the three.

RequirementTypicalWhy it decides the site
Power100 to 1,000 megawatts for a large new campus, often built in phasesThe site is only as good as the date the utility can deliver the load, and new plants, lines and substations take years to build.
LandTens to hundreds of acres beside high voltage lines and a substationParcels near transmission with room for later phases are few, and many are already held by other companies.
Water and coolingSet by the cooling design: evaporative, closed loop or air cooledA campus cooled by evaporation draws on the same system as homes and farms, and the county will ask how much.
FiberSeveral diverse long haul routes and short distances to usersA campus without redundant fiber paths cannot sell its capacity, and new routes across private land take time to build.
Backup generationGenerators and fuel to carry the full load through a grid outageDiesel engines must meet federal emission standards and need an air permit, and neighbors hear them run their tests.
Equipment taxSales tax on servers and equipment, paid again at every refreshServers are replaced every few years, so the state treatment of equipment is a cost the campus meets for its whole life.

Sources Electric Power Research Institute, Powering Intelligence: Analyzing Artificial Intelligence and Data Center Energy Consumption; U.S. Department of Energy, report on electricity demand from data centers (Lawrence Berkeley National Laboratory); Code of Virginia, section 58.1-609.3, subdivision 18; U.S. Environmental Protection Agency, Stationary Engines (NSPS and NESHAP); Staatscourant, Voorbereidingsbesluit hyperscale datacenters; Government of the Netherlands, cabinet restricts locations for hyperscale data centers; Netbeheer Nederland, national grid capacity map; Germany, Energy Efficiency Act (EnEfG), section 11; Germany, Federal Building Code (BauGB), section 2; Natural Resources Canada, Powering Canada's Future: A Clean Electricity Strategy.

02 How the decision gets made

The utility and the county set the pace of a campus.

Each step has a different owner inside the company, and the power answer comes first.

  1. 01 The load and the date Infrastructure and finance set how many megawatts are needed, when the first hall must be live, and how the load grows phase by phase. Where it stallsThe forecast changes after the utilities have already been asked for capacity.
  2. 02 The power screen The energy team asks utilities and public power boards which substations and lines can carry the load, on what date and at whose cost. Where it stallsEvery candidate site is waiting in the same connection queue.
  3. 03 Site diligence Real estate and engineering check parcels near capacity for zoning, soils, flood risk, fiber routes and the water and sewer service the local system can supply. Where it stallsThe best parcel belongs to another company and is not for sale.
  4. 04 The incentive package Tax and government affairs work through the sales tax treatment of equipment and the property tax abatement with two or three finalist states and their counties. Where it stallsThe conditions that apply years later get less attention than the headline value.
  5. 05 The supply contracts The power contract, the substation agreement and the water supply agreement are negotiated with the utility, the public power board and the water provider. Where it stallsThey are left until after the announcement, when the company can no longer walk away.
  6. 06 The county vote The county or city decides the zoning, the abatement and the water and sewer service after a public hearing, and the board approves the campus. Where it stallsResidents organize on noise, water and power bills before the project has made its case.
03 Where these projects go

Campuses go where a utility can still deliver power.

Data center campuses first clustered where fiber and power met near large cities, then spread to wherever a utility could still deliver hundreds of megawatts. A colocation building still wants to sit close to its tenants and their networks. A training campus can sit farther out, because the model does not care where it is trained. In every case the site turns on which utility can serve the load, and when.

  1. Northern Virginia and the Mid Atlantic The densest concentration of data centers in the country, built on fiber and early demand, where power delivery sets the pace of growth.
  2. Texas Its own grid, large tracts of land and fast growing cities draw campuses of every kind, from colocation near Dallas to large training sites.
  3. The Midwest and Ohio Valley Available land and generation, Great Lakes and river water, and states that have prepared large sites served by high voltage lines.
  4. Arizona and the Southwest Room for large campuses and fast growing metro areas, with water supply and cooling design central to every project.
Abroad
  1. The Netherlands National rules have confined the largest data centers, above 10 hectares and 70 megawatts, to a few designated areas; municipalities zone the land; and where the grid is congested, large new users wait in a queue for capacity.
  2. Germany The municipality decides land use through its own development plans, and federal law sets the energy efficiency, waste heat reuse and renewable electricity requirements a data center has to meet.
  3. Canada Electricity generation, transmission within a province and distribution are provincial matters, so whether and on what terms a large campus is served is decided province by province, through the provincial utility and its regulator.
04 Who decides

The county and its utility decide most campus terms.

Washington sets a few rules. The power, the water, the tax treatment and the vote are decided closer to the site.

LevelBodyWhat it controls
FederalEnergy (DOE)Programs and loans that finance new generation, storage and on site power for large loads
FederalEPAEmission standards for the stationary diesel and gas engines used as backup generators
StateState development agencyThe incentive agreement; in Virginia, the memorandum a campus signs to claim the equipment exemption
StateState revenue departmentSales and use tax on servers and equipment, and whether a campus has met the exemption terms
StateUtility commissionThe utility's rates and the terms it may set for very large new loads
LocalCounty or cityZoning, property tax abatement, water and sewer capacity and the public hearing
LocalUtilityThe supply contract, the substation and the date power arrives
ForeignForeign investorsSovereign and pension funds abroad that put equity into campuses and their power supply
05 What companies get wrong

Mistakes that delay a campus or raise its cost.

A company sites a large campus a few times a decade. The utility, the county and the state agency handle large load requests constantly, and inside the company infrastructure, real estate and tax each hold one piece of the deal.

  1. 01Making an offer on land before the utility has confirmed it can serve the load. A parcel beside a substation is worth little if the lines behind it are full. We find and check sites for deliverable power, water and zoning before the company makes an offer, and its broker and attorney handle the purchase or lease. Land, warehouse and industrial space →
  2. 02Comparing utilities on the posted rate alone. For a very large load the cost sits in the contract: who pays for the substation, minimum payments, the delivery date and the penalty if the load arrives late. We compare grid, on site and dedicated supply and negotiate those terms with the utility. Power and water →
  3. 03Bringing the county a water figure it cannot check. A board that cannot verify the draw on its system delays the vote or attaches conditions. We compare the cooling and water supply options and negotiate the supply terms with the water provider before the hearing. Power and water →
  4. 04Treating the sales tax exemption on equipment as permanent. Servers are replaced every few years, and an exemption can carry investment, job and wage conditions the campus has to keep meeting. We find every program the campus qualifies for and negotiate the package to a signed agreement with conditions it can meet. Incentives and tax →
  5. 05Announcing the site before the power terms and the package are signed. Once the site is public, the utility and the county know the project has nowhere else to go. We compare states and sites on what each will cost to build and run, so a second finalist stays real until the terms are signed. Site selection and relocation →
06 How we help

What we do for data center builders.

One team works the site, the incentives, the power and the water together, and the people you meet are the people who do the work.

All services →
  1. 01Power and water A comparison of grid, on site and dedicated supply, and power and water supply terms negotiated with the utility and the water provider.
  2. 02Land, warehouse and industrial space Sites near power capacity, found and checked for power, water and zoning before you make an offer.
  3. 03Incentives and tax Every state and local program the campus qualifies for, negotiated to a signed agreement with conditions you can meet.
From our work
Transaction supportCompleted

A complex transaction between two Fortune 100 companies for a new AI project

Decision
A parcel of more than 500 acres under a real estate option, part of a transaction between two Fortune 100 companies for a new AI project, with a grid demand of more than 2 gigawatts.
What we did
Retained first for site selection discovery on the parcel, then asked to find solutions to the power demand. Directly supported the transaction throughout.
Outcome
The transaction completed, and the AI project could go ahead.
A Fortune 100 technology company · Power and water
07 Questions

What people ask about this industry.

How much power does a data center need?

A large new campus commonly draws 100 to 1,000 megawatts, about the load of 80,000 to 800,000 homes. A campus goes up faster than the power plants, transmission lines and substations that serve it, which take years to plan and build, so the date the utility can deliver the load usually decides the site.

What matters most in data center site selection?

Power first: a utility that can deliver the load on a known date. Then land near high voltage lines, a water supply or cooling design the county accepts, diverse fiber routes and the state sales tax treatment of servers and equipment, and a county willing to zone and approve the campus.

How much water does a data center use?

It depends on the cooling design. A campus cooled by evaporation uses a large and steady amount of water, mostly in hot weather. Closed loop and air cooled designs use far less water but more power. The county and the water provider want the figure before they approve service.

Do data centers get tax breaks?

Many states exempt data center servers and equipment from sales and use tax, usually with conditions. Virginia, for example, requires a minimum new investment, new jobs at one and one half times the local average wage, and a memorandum of understanding with its development agency. Counties may also abate property tax.

Who approves a new data center?

The county or city decides zoning, property tax abatement and water and sewer service, usually after a public hearing. The utility decides how and when it can serve the load, under rates its state utility commission approves. The state sets the sales tax treatment of equipment, and backup generators need an air permit.

Get in touch

Tell us the load and when you need power.

Name the megawatts, the cooling design and the states you are weighing. We reply within two business days.

  • info@auerbridge.com
  • Replies within two business days
  • We represent companies and advise governments, never both sides of one transaction
I am