Semiconductor fab site selection starts with water and power.
Semiconductor fab site selection turns on a few things that rarely sit together: millions of gallons of ultrapure water a day and the wastewater capacity to match, a very large and very steady power supply, still ground, gas and chemical suppliers close by, and thousands of trained workers. We compare states and sites, negotiate the incentives, and compare and negotiate the power and water supply.
- About 10 million gallons of ultrapure water a day
- As much energy a year as about 50,000 homes
- Electricity is 5 to 30 percent of operating cost
A chip plant needs water and power before land.
Foundries that make chips for other companies, makers of their own logic or memory chips, mature node and analog fabs, packaging and test plants, and the gas, chemical, materials and equipment suppliers that follow them. The table describes a wafer fab.
| Requirement | Typical | Why it decides the site |
|---|---|---|
| Water | About 10 million gallons of ultrapure water a day, and wastewater capacity to match | The city or water district has to supply and treat volumes on the scale of a town. |
| Power | As much energy a year as about 50,000 homes, with very few interruptions | A dip in voltage can scrap the wafers in process, so reliability matters as much as size. |
| Ground | Stable soils and low vibration, away from heavy rail, quarries and busy highways | Small vibrations ruin wafers, which rules out many otherwise good industrial sites. |
| Gases and chemicals | Gas plants, chemical suppliers and hazardous waste handling nearby | A fab uses specialty gases and chemicals around the clock, so suppliers build beside it or within trucking distance. |
| Workforce | Several thousand engineers and technicians, and more during construction | Technicians take time to train, so the region needs colleges that can grow with the plant. |
| Room to grow | Land for several fab phases and for suppliers on or beside the site | Chip makers add fabs in phases, and a site too small for them forces a second search. |
Sources National Institute of Standards and Technology, CHIPS for America notice of funding opportunity (CARISSMA); United States Code, 15 U.S.C. 4652, semiconductor incentives; United States Code, 26 U.S.C. 48D, advanced manufacturing investment credit; Code of Federal Regulations, 40 CFR part 469, electrical and electronic components; European Commission, guidance on Integrated Production Facility and Open EU Foundry status under the Chips Act; Germany, Federal Building Code (BauGB), section 2; Innovation, Science and Economic Development Canada, semiconductor advanced packaging investment in Bromont, Quebec; Natural Resources Canada, Powering Canada's Future: A Clean Electricity Strategy.
Several teams inside the company share a fab site decision.
- 01 The product and capacity case Strategy, finance and technology set the process, the wafer output and how many phases the site must hold. Where it stallsThe case changes after states and utilities have been asked for capacity.
- 02 The state screen Real estate and operations compare regions on water, power, workforce, suppliers and what each state offers. Where it stallsStates are ranked on the incentive offer before water and power are checked.
- 03 Site diligence Engineering tests candidate sites for soils, vibration, flood risk, water, wastewater and the distance to suppliers. Where it stallsVibration is measured after the site is shortlisted.
- 04 The incentive package Tax and government affairs negotiate grants, tax abatement and training funds with two or three finalist states. Federal chip incentives expect a state or local offer. Where it stallsClawback and job terms get less attention than the headline value.
- 05 The utility agreements Energy and facilities negotiate the power, substation, water and wastewater agreements with the utility and the city. Where it stallsThey are left until after the announcement.
Fabs go where earlier fabs built a supplier base.
New fabs cluster around older ones, where trained technicians, gas and chemical plants and water systems built for the industry already exist. Packaging, test and supplier plants follow the fabs. Abroad, a different level of government approves the support.
- Arizona and the Southwest A long established fab cluster around Phoenix with a deep technician workforce and supplier base, where water planning shapes every project.
- Texas Fabs around Austin and Dallas, its own power grid and fast growing cities that supply engineers.
- The Pacific Northwest Oregon and Washington have hosted fabs for decades, with hydropower and a trained workforce around Portland.
- Upstate New York and the Midwest Plentiful fresh water, available power and states that have prepared very large sites for fabs and their suppliers.
- Germany A federal or state grant to a chip plant is state aid, so the European Commission assesses and approves it under EU rules. The municipality prepares the land use plan for the site.
- Canada Canada builds chip assembly, test and packaging plants with federal and provincial support. Electricity is a provincial matter, so power terms are set with the provincial utility.
The state, the city and the utility decide most terms.
| Level | Body | What it controls |
|---|---|---|
| Federal | Commerce | Federal chip manufacturing incentives for fabs, packaging, materials and equipment plants |
| Federal | Treasury and IRS | The investment tax credit for chip plants and equipment, and the rules for claiming it |
| Federal | EPA | National wastewater standards for semiconductor plants, applied through state and city programs |
| State | State development agency | Grants, job credits, training funds and the package for the largest projects |
| State | Utility commission | The utility's rates and the terms it may set for very large new loads |
| Local | City or county | Zoning, property tax abatement, roads and the water and wastewater service |
| Local | Utility | The supply contract, the substation and the date power arrives |
| Foreign | Home governments | Agencies of a foreign parent's home country that finance or approve investment abroad |
Mistakes that raise the cost of a fab.
A chip maker sites a fab rarely, while states, cities and utilities field large plant requests every year. Inside the company, no single team owns the whole deal.
- 01Ranking states on the incentive offer before checking water and power. The largest package is worth little if the water system or grid cannot serve the plant on time. We compare states and sites on what each will cost to build and run, with water and power priced in. Site selection and relocation →
- 02Assuming the city can treat the wastewater because it can supply the water. Wastewater treatment is often the tighter limit, and expanding a treatment plant is a public project on the city's schedule. We compare supply and treatment options and negotiate the water and wastewater terms with the provider. Power and water →
- 03Treating the headline value of the package as the deal. Clawbacks and job targets decide what a fab keeps. We find every program the plant qualifies for and negotiate the package to a signed agreement with terms the plant can meet. Incentives and tax →
- 04Announcing the site before the package and utility terms are signed. Once the site is public, the state, city and utility know the company has nowhere else to go. We keep two sites in the comparison until the package and the supply terms are agreed. Site selection and relocation →
What we do for chip makers and their suppliers.
One team works the site, the incentives, the power and the water together, and the people you meet are the people who do the work.
- 01Site selection and relocation States and sites compared on water, power, ground, workforce and suppliers, and on what each will cost to build and run.
- 02Incentives and tax Every program the plant qualifies for, negotiated with the state and local agencies to a signed agreement.
- 03Power and water Supply options compared and power and water terms negotiated with the utility and water provider.
What people ask about this industry.
How much water does a semiconductor fab use?
NIST puts the average chip fab at about 10 million gallons of ultrapure water a day. The plant needs wastewater treatment capacity to match, so the local water and sewer system often decides whether a site works.
How much power does a semiconductor fab need?
NIST says a typical semiconductor plant uses as much energy in a year as about 50,000 homes, and electricity is 5 to 30 percent of its operating cost. The supply has to be very reliable, because a dip in voltage can scrap wafers.
What is the difference between a fab and a foundry?
A fab is any plant that makes chips on silicon wafers. A foundry is a fab that makes chips designed by other companies. Some companies make their own chips in their own fabs; others design chips and pay a foundry to make them.
What decides where a semiconductor fab is built?
Water and wastewater capacity first, then a large and very reliable power supply, ground free of vibration, nearby suppliers, trained workers and room for later phases. Incentives matter once those are met.
Our research on this industry.
Tell us about the fab or supplier plant you are siting.
Name the plant, the water and power it needs and the states you are weighing. We reply within two business days.
- info@auerbridge.com
- Replies within two business days
- We represent companies and advise governments, never both sides of one transaction