Transportation manufacturing site selection needs scarce land and trained workers.

This group holds vehicle assembly and battery plants, aircraft and engine plants, and shipyards. Their sites need land few places offer, a megasite with rail or a parcel on a runway or deep water, and a workforce the state helps train. We compare the sites, negotiate the incentives and the power and water supply, and package the federal financing.

A body shop in elevation: a car body on a floor conveyor, two welding robots on pedestals and an overhead gantry
  • Megasites of 1,000 acres or more
  • A runway or deep water at the site
  • Skilled trades take three to five years to learn
01 The market

Carmakers, aircraft builders and shipbuilders build these plants.

Vehicle makers, battery cell makers and their largest suppliers build some of the largest private factories in North America. Airframe and engine makers, space hardware builders and shipbuilders build some of the largest buildings in industry. A carmaker chooses a new plant site perhaps once a decade, and an aircraft builder or a shipyard adds a line or a yard about as often.

Assembly plants cluster where earlier plants built a supplier base and a trained workforce, and where states prepared very large sites in advance; battery plants follow the assembly plants they feed. Aircraft plants go where earlier plants left machinists, runways and suppliers, and shipyards sit only where deep water and room for dry docks exist. Washington buys much of what the aircraft plants and yards make. The site is decided by the state, the county, the utility and, for aircraft and ships, the airport or port that controls access.

02 What these projects share

Scarce sites and trained workers decide these plants.

  1. Scarce land An assembly or battery plant needs 1,000 contiguous acres or more in one ownership. An aircraft plant needs a runway and a yard needs deep water, land that rarely comes up for sale.
  2. Suppliers nearby Seats, cells and modules arrive at an assembly line in sequence, and castings, forgings and composites feed an aircraft line. A site with no room for suppliers costs more every year.
  3. State training An auto plant hires several thousand people at once, and shipyard trades take three to five years to learn, so state training programs carry much of the load.
  4. Federal demand Federal tax credits for battery components, naval and military orders, and shipyard grants and loan guarantees shape where these plants are built.
  5. Local boards The county, the development authority or the airport or port board signs part of the deal, and a board that learns the details late can slip its vote.
03 Industries in this group

How the finished product leaves sets each site apart.

  1. Automotive, EVs and batteries Decided by a ready megasite with power, water and rail built, land for suppliers within about an hour, and a workforce the state will train. The page covers what an assembly or battery plant needs, the package, the power contract and where plants cluster.
  2. Aerospace, space and shipbuilding Decided first by a runway or deep water at the edge of the site, then by machinists, welders and assemblers who take years to train. The page covers aircraft, engine and space hardware plants and shipyards, airport and port access terms, and the federal programs behind the demand.
What each needs first
IndustryFirst requirementSecond requirement
Automotive, EVs and batteries Land1,000 contiguous acres or more, flat, in one ownership, with room to expandPowerTransmission level service and a dedicated substation; cell plants need far more
Aerospace, space and shipbuilding WorkforceMachinists, welders, fitters and assemblers, who take years rather than months to reach proficiencyAirfield or waterAerospace: a runway on or beside the site. Yards: deep water frontage and a channel

Sources Tennessee Code, section 64-6-103, megasite certification; U.S. Government Accountability Office, Shipbuilding and Repair: Navy Needs a Strategic Approach for Private Sector Industrial Base Investments (GAO-25-106286); Fraunhofer Research Institution for Battery Cell Production FFB, energy consumption of battery cell factories. Each industry page lists the sources for its own figures.

04 What companies get wrong

Mistakes that raise the cost of these plants.

These are taken from the industry pages, where each is set out in full.

  1. 01 Automotive, EVs and batteriesTreating a certified megasite as a finished one. Certification says the land is assembled; the substation, the water line and the rail spur may still be unbuilt. We score each site on what is built and funded on the day you commit. Site selection and relocation →
  2. 02 Automotive, EVs and batteriesLeaving power and water until after the announcement. Once the site is public the utility knows the plant has nowhere else to go. We negotiate the power contract and the water supply alongside the package, while two sites are still in play. Power and water →
  3. 03 Aerospace, space and shipbuildingTreating land beside an airport as land with runway access. Access to a public runway depends on the airport sponsor and the federal grant obligations it carries, and the terms bind for decades. We test the access and its terms before a parcel reaches the shortlist. Site selection and relocation →
  4. 04 Aerospace, space and shipbuildingConsidering federal programs after the site is chosen. Shipyard grants and ship financing guarantees have their own eligibility and application rules, and a project shaped without them may not qualify. We match the project to the federal programs it fits while the site is still open. Federal programs and financing →
05 How we help

What we do for transportation and defense manufacturers.

A carmaker or an aircraft builder adds a plant perhaps once a decade, while the state agency, the utility and the airport or port authority negotiate these deals all the time. Inside the company, real estate, tax, finance and government affairs each own a piece, and nobody owns all of it.

All services →
  1. 01Site selection and relocation Megasites, airfield and waterfront sites compared on the access, workforce, supplier land and package each can deliver.
  2. 02Incentives and tax Job credits, training money, site grants and abatements negotiated with the finalist states and local bodies, on terms the plant can meet.
  3. 03Power and water Power and water supply terms negotiated with the utility and the water provider while more than one site is in play.
  4. 04Federal programs and financing Shipyard grants, ship financing guarantees and industrial base programs matched to the project and built into its financing plan.

One team works the site, the incentives, the power and the water together, and the people you meet are the people who do the work.

06 Questions

What people ask about these projects.

What do auto plants, aircraft plants and shipyards need in a site?

Each needs land few places offer, suppliers within reach and a trained workforce. An assembly or battery plant needs a megasite of 1,000 acres or more. An aircraft plant needs a runway on or beside the site, and a shipyard needs deep water and room for dry docks.

Why are sites for vehicle and aircraft plants so hard to find?

Few megasites sit under one owner with the earthwork done, and a certified one may still lack its substation, water line or rail spur. Land beside a runway or on deep water rarely comes up for sale, and access to a public runway depends on the airport sponsor, so expanding an existing plant or yard often wins.

How much power do battery plants and aircraft plants need?

An assembly plant needs transmission level service and a dedicated substation, and a battery cell plant needs far more: roughly 20 to 40 kilowatt hours of energy for each kilowatt hour of cell capacity. Aircraft plants and shipyards need industrial service with large, uneven loads from test cells, autoclaves and welding.

Get in touch

Tell us what the plant or yard will build.

Name the states, airports or ports in play and when production starts. We reply within two business days.

  • info@auerbridge.com
  • Replies within two business days
  • We represent companies and advise governments, never both sides of one transaction
I am