Steel mill site selection starts with the power contract.
Steel mill site selection turns on electricity before anything else. An arc furnace mill melts scrap with power and a primary aluminum smelter uses many times more, so the rate, the capacity and the terms of the contract decide the site, followed by scrap, rail or river, water and a local government that agrees. We compare the sites and negotiate the power and the incentives together.
- 300 to 525 kWh per ton of arc furnace steel
- About 13,000 kWh per ton of primary aluminum
- Most United States steel comes from arc furnaces
Electricity is the largest running cost of a mill.
Steelmakers, aluminum smelters and rollers, and other metals producers turn scrap and ore into the coil, plate, bar and sheet other factories buy. The table compares a new electric arc furnace mill with a primary aluminum smelter.
| Requirement | Typical | Why it decides the site |
|---|---|---|
| Power use | Mill: 300 to 525 kWh per ton of steel. Smelter: about 13,000 kWh per ton | Electricity is the largest running cost of both, and a smelter uses roughly thirty times as much per ton as a mill. |
| Power contract | Mill: often interruptible service. Smelter: firm supply for decades | A furnace can pause when the utility calls; a smelter runs continuously, so it needs a long contract at a price that holds. |
| Feedstock | Mill: scrap, plus pig iron or direct reduced iron. Smelter: imported alumina | Scrap and alumina are heavy, traded commodities, so the plant sits where they can be gathered or landed cheaply. |
| Rail and river | Rail service, and barge or deep water for the heaviest flows | Scrap, alumina and finished coil move in bulk, and freight on every ton in and out compounds over the life of the plant. |
| Water | Steelmaking: 13,000 to 23,000 gallons of fresh water per ton | Most of it cools furnaces and equipment, so supply and discharge capacity have to be in place before the first heat. |
| Land | A very large flat site with room for scrap yards, rail loops and a second line | Few sites combine that acreage with rail, river and transmission, and many have to be assembled from several owners. |
Sources Lawrence Berkeley National Laboratory, Energy Efficiency Improvement and Cost Saving Opportunities for the U.S. Iron and Steel Industry (ENERGY STAR Guide); U.S. Environmental Protection Agency, Energy Trends in Selected Manufacturing Sectors: Alumina and Aluminum; U.S. Environmental Protection Agency, Energy Trends in Selected Manufacturing Sectors: Iron and Steel; U.S. Geological Survey, Mineral Commodity Summaries: Iron and Steel; U.S. Geological Survey, Mineral Commodity Summaries: Aluminum; Tennessee Valley Authority Office of Inspector General, TVA's Interruptible Pricing Products; Hydro-Québec, Rate L: Industrial Rate for Large-Power Customers; Gazette officielle du Québec, government decree on electricity supplied by Hydro-Québec to an aluminum smelter; German Emissions Trading Authority (DEHSt), Electricity Price Compensation.
The power screen comes before the site shortlist.
A metals company builds a new mill or smelter rarely, and most follow the steps below in this order.
- 01 The product and the market Strategy decides what the plant makes, flat or long steel, sheet or primary aluminum, and which customers must sit within freight distance. Where it stallsThe product is fixed before anyone knows what power will cost.
- 02 The power screen Energy and procurement ask utilities and public power providers for the capacity, the rate, interruptible terms and the date power can arrive. Where it stallsEarly quotes come before the load study and change once it is done.
- 03 The site short list Real estate and engineering test each site for transmission, rail, barge, water, soils and the scrap or alumina supply around it. Where it stallsA site with river and rail lacks the transmission to carry the load.
- 04 The package Tax, finance and government affairs negotiate abatements, payments in lieu of taxes, bonds and training with two or three finalist states. Where it stallsTerms written around job counts fit a capital heavy plant poorly.
- 05 Contracts and local votes The utility contract is signed and, where required, approved by the state commission; the county or parish votes on the abatement while counsel and engineers handle air and water permits. Where it stallsCommission approval or the permit schedule ends up setting the start date.
Arc furnace mills spread far beyond the Great Lakes.
Integrated mills cluster around the Great Lakes, near ore, coal and the carmakers they supply. Arc furnace mills need no coal and depend less on water transport, so they are spread far more widely and go where scrap, power and customers meet. Primary aluminum smelters go wherever a long term power contract can be had, and close when it ends. Across the border, the level of government that sets the power price is different.
- The Great Lakes and Ohio Valley Indiana makes more raw steel than any other state, with Ohio and Pennsylvania close behind: an old customer base, rail and river, and a trained workforce.
- The Mississippi River and the Gulf Barge and deep water ports bring in scrap, pig iron and alumina and carry out coil, at freight costs land routes cannot match.
- The Southeast and Texas Arc furnace mills built close to fast growing construction and automotive demand, with large sites and utilities able to serve big loads.
- The Pacific Northwest Federal hydropower once drew a large share of the country's smelters, and their closures showed how closely a smelter follows its power contract.
- Canada Canada smelts several times as much aluminum as the United States, on hydropower. In Québec the provincial Crown utility sells under regulated rates, but the government can set the terms of a special contract for a smelter itself.
- Germany Germany is a large steel producer with both blast furnace and arc furnace mills. The federal government compensates electricity intensive plants, steel among them, for part of the carbon cost in their power price, within European Union state aid rules.
The utility and the county decide the plant.
Federal rules and trade policy set the backdrop. The plant is decided by the utility, the state and the county or parish.
| Level | Body | What it controls |
|---|---|---|
| Federal | Department of Energy | Loans, loan guarantees and grants for industrial plants |
| Federal | EPA | The federal air and water rules that state agencies apply when they permit a melt shop or potline |
| Federal | Commerce and USTR | Trade policy that shapes where it pays to make steel and aluminum |
| State | Development agency | Megaproject packages, job credits, site grants and training for furnace and rolling crews |
| State | Utility commission | Approval of the rates and special contracts an investor owned utility offers a very large load |
| Local | County, parish or port | The property tax agreement, the bond structure, the site and the rail or dock work |
| Local | Utility or public power | The power rate, interruptible terms, the substation and the date power arrives |
| Foreign | Home governments | Export credit and investment agencies in the owner's home country that can finance part of the plant |
Mistakes that delay a mill or raise its cost.
A metals company builds a mill or smelter perhaps once a generation. The utility and the state across the table price large loads every month, and inside the company energy, real estate and tax each hold one piece.
- 01Treating the utility's first rate quote as the price. The first number comes before the load study, the transmission work and the contract terms, and each one moves it. We negotiate the power contract and the substation schedule while two sites are still competing. Power and water →
- 02Buying firm power for a furnace that could run interruptible. An arc furnace can pause on short notice, and utilities pay for that flexibility through interruptible rates. We price firm and interruptible service at each site and write the choice into the contract. Power and water →
- 03Choosing a site for its river and rail before checking transmission. A site with barge, rail and acreage can sit miles from a line able to carry the load. We score each site on the transmission and substation the utility can deliver by your start date. Site selection and relocation →
- 04Signing incentive terms written for a different kind of plant. A mill's value sits in its furnaces and rolling lines, and job targets copied from an assembly plant are easy to miss. We negotiate abatements, payments in lieu of taxes and bonds tied to what the plant will do. Incentives and tax →
- 05Leaving the water supply until after the site is chosen. Steelmaking uses 13,000 to 23,000 gallons of fresh water per ton, and supply and discharge capacity have to be in place before the first heat. We negotiate the water supply with the provider alongside the power contract, while two sites are still competing. Power and water →
What we do for steel and aluminum producers.
One team works the site, the incentives, the power and the water together, and the people you meet are the people who do the work.
- 01Site selection and relocation A scored shortlist of sites with the transmission, rail, river, water and scrap or alumina supply each one can deliver by your start date.
- 02Power and water A power contract for a very large load, firm or interruptible, with the substation, the rate and the water supply settled before you commit.
- 03Incentives and tax Abatements, payments in lieu of taxes and bonds negotiated across competing states, with terms a capital heavy plant can meet.
What people ask about this industry.
How much electricity does an electric arc furnace use?
An arc furnace uses roughly 300 to 525 kilowatt hours of electricity per ton of steel, with about 400 a common average. A mill melting a million tons a year therefore uses on the order of 400 million kilowatt hours, which is why power decides where these mills go.
How much electricity does it take to make a ton of aluminum?
A modern primary smelter uses about 13,000 kilowatt hours per metric ton of aluminum, and older smelters used up to 20,000. Recycled aluminum needs about five percent of that energy, which is why smelters locate where long term power is cheapest.
How does a large industrial power contract work?
A very large plant signs a contract with its utility or public power provider that sets a demand charge for capacity, an energy charge per kilowatt hour, a minimum bill, the term and who pays for the substation. Investor owned utilities usually need state commission approval; interruptible terms lower the rate.
Why are steel mills built near rivers?
Scrap, pig iron, alumina and finished coil are heavy and move in bulk, and barge freight is cheap. Mills also draw large amounts of cooling water. Arc furnace mills depend less on water transport than blast furnace mills, so they are spread more widely.
How much water does a steel mill use?
Steelmaking uses about 13,000 to 23,000 gallons of fresh water per ton, most of it lost to evaporation while cooling furnaces and equipment. Counting water that is recycled inside the plant, the figure is closer to 75,000 gallons per ton.
Our research on this industry.
Tell us the metal and the tonnage you plan to make.
Name the states in play and when you need power. We reply within two business days.
- info@auerbridge.com
- Replies within two business days
- We represent companies and advise governments, never both sides of one transaction